Phase 2 of the SWAR Project is now Complete

The SWAR Project consists of 3 phases.
2_swarprojectupdate-aug8
Town of BWG Photo

Phase 2 of construction of the South West Arterial Road (SWAR) at Sideroad 10 (between Line 5 and Line 6) has now reopened as of Friday, August 4, at 4 pm.

Phase 3 Will begin on August 8 and requires the closure of at Sideroad 10 between Line 6 and Brookview Avenue from August 8 to October 20, 2023.

This closure will allow the Contractor to complete the reconstruction of this portion of Sideroad 10, including the replacement of the Fraser Creek culvert with new concrete box culverts.

 